Project Description
GLOBALFOUNDRIES will invest 1.2 billion EUR in the expansion of their wafer manufacturing facility in Dresden (Germany). Until 2012, the plant shall be one of the largest in the world. The expansion will see a new facility constructed at Fab 1 that will add nearly 10,000 square meters of cleanroom space to scale the output of 300 mm wafers to 80,000 per month.
| Project type: | Semiconductor plant |
| Location: | Germany (Dresden) |
| Investment amount: | 1,2 billion EUR |
| Area: | 10,000 m² |
| Investor: | GLOBALFOUNDRIES |
| Time period: | 01.04.2010 – 30.09.2011 |
| Perfomance: | Time scheduling |
Overall planning / scheduling for the phases of design, procurement, construction and start up of the entire project. This includes the construction of the buildings, the technical und processing facilities, the installation of the sterilized spaces as well all phases of assembly of equipment and functioning of the plant.