Project Description
EVC-1 covers the energy requirements of the new AMD (Advanced Micro Devices) microchips production and development center. The production increase requires an extension of the energy infrastructure which will be carried out during the current installation operations.
| Project type: | Co-Generation power plant |
| Location: | Germany (Dresden) |
| Investor: | EVC Dresden-Wilschdorf GmbH & Co. |
| Time period: | 01.06.2006 – 30.06.2008 |
| Performance: | Project planning and control |
Overall scheduling for planning, acquisition, construction / installation, startup of the extension during running operation at the Energy Center. Repeat assignment after extension in 2002.