ITER TB04
France

Project Description

In international association, the world’s first fusion reactor is being built in Cadarche/Southern France. ITER will be the world’s largest experimental fusion facility and is designed to demonstrate the scientific and technological feasibility of fusion power.
A Franco-German consortium (GDF Suez Group & M+W Group) has awarded a contract for a major partial project. The contract covers the design, supply, installation and commissioning of the mechanical and electrical equipment of the Tokamak complex which consists of the Tokamak, Diagnostic and Tritium buildings plus the surrounding buildings which reach a total of 97,200 m³.

Project type: Nuclear fusion reactor
Location: France (Cadarache)
Investment amount: 580 million EUR
Investor: ITER Organisation
Period: 01.07.2013 – 31.12.2018
Performance: Head of planning and control department and document control for TB04
Project planning and control
Technical interface management

General Schedule Management and document control management: Head of the scheduling and document control team
Management of the entire scheduling of the consortium. Coordination and integration of all schedules created by the consortium.
Progress monitoring and calculation of EV key figures as a basis for the invoicing. Reporting to the F4E and IO.
Organisation and realization of the entire document control of the consortium. This includes the management of all documents issued by the consortium (planning documents, correspondence, meeting minutes, etc.) as well as the administration and distribution of all incoming documents.
Project planning and control
Technical Interface Management – managing of existing interface  database as well as coordinating the requirements of the interface requester and provide.

More reference projects

University Clinic Jena
Germany
Angra 3