Angstrem Fab Upgrade / Energy Supply Center (ESC)

Project Description

A semiconductor plant wich was established in 1991 will be extended for the production of 200 mm wafers. The new Anstrem-T production site shall have a clean room aera of 6,000 m². An additional building for gas, chemical and ultrapure water supply will be erected as well as a natural gas-powered energy supply center for electricity, heating and cooling.

Project type: Semiconductor plant
Location: Russian Federation  (Moskau/Zelenograd)
Investment amount: 150 million EUR
Investor: Anstrem-T JSC
Time period: 01.04.2008 – 31.07.2010
Performance: Time scheduling

Preparing of contract schedules as well as overall planning and project control for design, procurement, construction and start up an enhancement of an existing fab, including cogeneration plant.

More reference projects

Wetfeet Global Tech I
SolarWorld Freiberg SF 3