Project Description
The latest fabrication facility of AMD / GLOBALFOUNDROES will come online through a Major transformation of the existing Fab 30 which will be named Fab 38 / Fab 1, Module 1. The transition from 200 mm to 300 mm allows for more than twice as many processors an a wafer.
| Project type: | Semiconductor plant |
| Location: | Germany (Dresden) |
| Investment amount: | 2.2 billion EUR |
| Investor: | AMD Saxony LLC & Co.KG GLOBALFOUNDRIES Dresden Modul Two GmbH & Co.KG |
| Time period: | 01.11.2006 – 31.12.2009 |
| Performance: | Superior time scheduling, exchange over all departments coordination of process tools. |
Time scheduling an coordination of insertion, disposition, hook-up and start-up of the production equipment.