On July 2, 2026, Infineon’s new semiconductor plant in Dresden officially began operations. Chips will be manufactured on 300-millimeter wafers in a cleanroom area spanning 20,000 square meters.
Infineon has invested approximately 2 billion euros (excluding production equipment for semiconductor manufacturing) in the plant.
The new factory building will be completed approximately 3 years after the groundbreaking in May 2023 and 3 months ahead of the original schedule.
This success is the result of a collaborative partnership among all companies involved in the project, as well as forward-looking scheduling and consistent project management. GPMS GmbH was commissioned by the general contractor to handle the entire project schedule (planning, procurement, construction, installation, and commissioning) and played a key role in ensuring that, despite the high technical requirements and the complexity of the construction project, quality, safety, and schedule targets were maintained at all times and, in particular, that the ambitious deadlines were met.